Plan of the Day: March 09

No work due to wet ground conditions.

 

Following work is anticipated for Monday 03/11/24 and Tuesday 03/12/24:

03/11/24:  Culvert Installation    C-102  700 E between 2400 N and 2500 N
                                                   RipRap @ C-4 3300 N between 1400 E and 1500 E

                Roadway Prep.          900 E between 2600 N and US 150
                                               800 E between 2500 N and 2750 N
                                               2700 N between 700 E and 800 E
                                              700 E between 2700 N and 3050 N

03/12/24:  Culvert Installation    C-103  700 E between 2400 N and 2500 N
                                                C-10   1400 E between 3100 N and 3200 N

                Roadway Prep.          Same locations as 03/11/24.

Anticipated work can be altered by weather, equipment breakdown and any other unforeseen circumstances.