Plan of the Day: March 11

Roads will be closed for road work preparation:

900E (from 2600N to US150),
800E (from 2500N to 2750N),
2700N (from 700E to 800E),
700E (from 2700N to 3050N),
700E (from 2400N to 2500N) with culvert work C-102,
3300N (from 1400E to 1500E) with riprap at C-4,

Roads will be reopened at the end of the day. 

 

03/12/24: 

Culvert Installation   
C-103  700 E between 2400 N and 2500 N
C-10   1400 E between 3100 N and 3200 N

Roadway Prep.         
Same locations as 03/11/24.

Anticipated work can be altered by weather, equipment breakdown and any other unforeseen circumstances.