Plan of the Day: March 16

Following roads will be closed for roadwork preparation:

1400E (from 3100N to 3200N) with culvert work at C-11,
CH5 (from 2400N to 2500N) riprap and FES @ C-61,
900E (from 2750N to 3050N),
700/725E (from 2750N to 3050N),
2750N (from CH5 to 1000E)

Roads will be reopened at the end of the day. 

 

In addition, the following work is anticipated  for Monday 03/18/2024 and Tuesday 03/19/2024:

Monday 03/18/2024:  Culvert installation: C-46  800 E between 2300 N and 2400 N
                                                                 C-104 725 E between 2300 N and 2400 N
                                                                  C-11 1400 E between 3100 N and 3200 N

                                  Roadway Prep.:     2400 N between 400 E and 725 E
                                                                 2500 N between 400 E and CH 5
                                                                 2600 N between 400 E and CH 5
                                                                   725 E between IL Rt 10 and 2500 N

Tuesday 03/19/2024:  Culvert installation: C-105  725 E between 2150 N and 2300 N
                                                                   C-106  725 E between 2150 N and 2300 N
                                                                    C-11  1400 E between 3100 N and 3200 N

                                   Roadway Prep.:    2400 N between 400 E and 725 E
                                                                 2500 N between 400 E and CH 5
                                                                 2600 N between 400 E and CH 5
                                                                   725 E between IL Rt 10 and 2500 N

Anticipated work can be altered by weather, equipment breakdowns or any other unforeseen circumstance.