Following roads will be closed for roadwork preparation:
1400E (from 3100N to 3200N) with culvert work at C-11,
CH5 (from 2400N to 2500N) riprap and FES @ C-61,
900E (from 2750N to 3050N),
700/725E (from 2750N to 3050N),
2750N (from CH5 to 1000E)
Roads will be reopened at the end of the day.
In addition, the following work is anticipated for Monday 03/18/2024 and Tuesday 03/19/2024:
Monday 03/18/2024: Culvert installation: C-46 800 E between 2300 N and 2400 N
C-104 725 E between 2300 N and 2400 N
C-11 1400 E between 3100 N and 3200 N
Roadway Prep.: 2400 N between 400 E and 725 E
2500 N between 400 E and CH 5
2600 N between 400 E and CH 5
725 E between IL Rt 10 and 2500 N
Tuesday 03/19/2024: Culvert installation: C-105 725 E between 2150 N and 2300 N
C-106 725 E between 2150 N and 2300 N
C-11 1400 E between 3100 N and 3200 N
Roadway Prep.: 2400 N between 400 E and 725 E
2500 N between 400 E and CH 5
2600 N between 400 E and CH 5
725 E between IL Rt 10 and 2500 N
Anticipated work can be altered by weather, equipment breakdowns or any other unforeseen circumstance.