Plan of the Day: March 20

Following roads will be closed for roadwork preparation:

700E (2150N to 2300N) culvert C-108,
2150N (700E to 800E) culvert C-110,
3300N (1400E to 1500E) culvert C-5,
2400N (400E to 700E),
2500N (700E to 900E),
2750N (CH5 to 1000E),
2600N (400E to CH5),
2500N (400E to CH5),
700E (RT10 to 2500N),
800E (RT10 to 2400N).

Roads will be closed by the end of the day.

 

In addition, the following work is anticipated for Thursday 03/21/2024 and Friday 03/22/2024:

Thursday 03/21/2024:  Culvert installation:  C-245 and C-244 A   2150 N between 525 E and 600 E
                                                                      C-5                           3300 N between 1400 E and 1500 E

                                      Roadway Prep.:   2400 N  between 400 E and 700 E            2500 N between 400 E and CH 5
                                                                   2500 N between 700 E and 900 E              700 E between IL Rt 10 and 2500 N
                                                                   2750 N between CH 5 and 1000 E             800 E between IL Rt 10 and 2400 N 
                                                                   2600 N between 400 E and CH 5 

Friday 03/22/2024:      Culvert installation    C-243 and C-248   2150 N between 525 E and 600 E
                                                                      C-26                     1200 E between 3300 N and 3400 N

                                     Roadway Prep.:       Same as Thursday 03/21/2024

Anticipated work can be altered by weather, equipment breakdowns or any other unforeseen circumstance.