No roadwork scheduled for March 23.
In addition, the following work is anticipated for Monday 03/25/2024 and Tuesday 03/26/2024:
Monday 03/25/2024:
Culvert Installation: C-243 & C-24 2150 N between 525 E and 600 E
C-13 3100 N between CH 5 and 1350 E
Roadway Prep.: 2600 N between 400 E and CH 5 700 E between 2150 N and IL Rt 10
2500 N between 400 E and CH 5 2150 N between 525 E and 800 E
2400 N between 400 E and 700 E 775 E between 2050 N and 2150 N
800 E between 2150 N and 2400 N 600 E between 2150 N and 3rd St.
Tuesday 03/26/2024:
Culvert Installation: C-218 2150 N between 600 E and 700 E
C-44 800 E between 2150 N and IL Rt. 10
C-23 1200 E between 3200 N and 3300 N
Roadway Prep.: Same as Monday 03/25/2024
Anticipated work may be altered by weather, equipment breakdowns or any other unforeseen circumstances.