Plan of the Day: March 23

No roadwork scheduled for March 23. 

In addition, the following work is anticipated for Monday 03/25/2024 and Tuesday 03/26/2024:

Monday 03/25/2024: 

Culvert Installation:  C-243 & C-24    2150 N between 525 E and 600 E
                               C-13                3100 N between CH 5 and 1350 E

Roadway Prep.:     2600 N between 400 E and CH 5        700 E between 2150 N and IL Rt 10
                            2500 N between 400 E and CH 5       2150 N between 525 E and 800 E
                            2400 N between 400 E and 700 E       775 E between 2050 N and 2150 N
                            800 E between 2150 N and 2400 N      600 E between 2150 N and 3rd St.



Tuesday 03/26/2024:

Culvert Installation:  C-218    2150 N between 600 E and 700 E
                               C-44      800 E between 2150 N and IL Rt. 10
                               C-23     1200 E between 3200 N and 3300 N

Roadway Prep.:    Same as Monday 03/25/2024


Anticipated work may be altered by weather, equipment breakdowns or any other unforeseen circumstances.