Following roads will be closed for roadwork:
- 800E (2150N to IL RT10) culvert work C-44,
- 1200E (3200N to 3300N) culvert work C-23 (riprap),
- 1100E (3300N to 3400N) culvert work C-237.
- 2600N (400E to CH5),
- 2500N (400E to CH5),
- 2400N (400E to CH5),
- 800E (2150N to 2400N),
- 600E (2150N to 3rd street),
- 2150N (525E to 800E),
- 775E (2050N to 2150N)
Roads will be reopened at the end of the day
In addition, the following work is anticipated for Thursday 03/28/2024 and Friday 03/29/2024:
Thursday 03/28/2024: Culvert Installation:
C-44 800 E between 2150 N and IL Rt 10
C-45 800 E between IL Rt 10 and 2300 N
C-237 1100 E between 3300 N and 3400 N
Roadway Prep.:
2600 N between 400 E and CH 5 600 E between 2150 N and 3rd St.
2500 N between 400 E and CH 5 2150 N between 525 E and 800 E
2400 N between 400 E and CH 5 775 E between 2050 N and 2150 N
800 E between 2150 N and 2400 N
Friday 03/29/2024: Culvert Installation:
C-45 (Riprap) 800 E between 2150 N and 2300 N
C-231 3200 N between 1000E and 1100 E
Roadway Prep.: Same as Thursday 03/28/2024
Anticipated work may be altered by weather, equipment breakdowns or any other unforeseen circumstance.