Plan of the Day: March 28

Following roads will be closed for roadwork and reopened at the end of the day 03/28/24:

  • 800E (2150N to IL Rt10) culvert work C-44,
  • 1100E (3300N to 3400N) culvert work C-237, 
  • 2600N (400E to CH5),         
  • 2500N (400E to CH5),         
  • 800E (2150N to 2400N)
  • 2150N (525E to 800E)

Following roads will be closed for roadwork and will be reopened on 04/05/24

  • 900E (2750N to US150)
  • 725/700E (2750N to 3050N)

In addition, the following work is anticipated for Friday 03/29/2024:


Friday 03/29/2024:   Culvert Installation: 

C-45 (Riprap) 800 E between 2150 N and 2300 N
C-231 3200 N between 1000E and 1100 E


Roadway Prep.:   

2600 N between 400 E and CH 5          600 E between 2150 N and 3rd St.
2500 N between 400 E and CH 5          2150 N between 525 E and 800 E
2400 N between 400 E and CH 5          775 E between 2050 N and 2150 N
800 E between 2150 N and 2400 N

Anticipated work may be altered by weather, equipment breakdowns or any other unforeseen circumstance.