Plan of the Day: May 02

Following roads will be closed and reopened at the end of the day:

  • 3200N (from 900E to CH2)
  • 900E (from 2750N to 3300N)
  • 1400E (from 3200N to 3300N) soil cement cure
  • 1500E (from 3200N to 3300N) soil cement cure

Following roads will be closed and reopened on 05/03/04:

  • 1500E (from 3200N to 3300N) soil cement cure
  • 700E (from 2750N to 3070N) C-51

Following roads will be closed and reopened on 05/04/24:

  • 3300N (from 1400E to 1500E) soil cement cure

In addition, the following work is anticipated for Friday 05/03/2024:            

Friday 05/03/2024:    4" Aggregate Cap                        1500 E between 3200 N and 3300 N

                                  Cement Stabilization                    1400 E between 3100 N and 3200 N
                                  Culvert Installation   (C-51)            700 E between 2750 N and 3070 N

Anticipated work can be altered by weather, equipment breakdowns, or any other unforeseen circumstance.