Following roads will be closed and reopened at the end of the day:
- 3200N (from 900E to CH2)
- 900E (from 2750N to 3300N)
- 1400E (from 3200N to 3300N) soil cement cure
- 1500E (from 3200N to 3300N) soil cement cure
Following roads will be closed and reopened on 05/03/04:
- 1500E (from 3200N to 3300N) soil cement cure
- 700E (from 2750N to 3070N) C-51
Following roads will be closed and reopened on 05/04/24:
- 3300N (from 1400E to 1500E) soil cement cure
In addition, the following work is anticipated for Friday 05/03/2024:
Friday 05/03/2024: 4" Aggregate Cap 1500 E between 3200 N and 3300 N
Cement Stabilization 1400 E between 3100 N and 3200 N
Culvert Installation (C-51) 700 E between 2750 N and 3070 N
Anticipated work can be altered by weather, equipment breakdowns, or any other unforeseen circumstance.