Tne following roads will be closed and reopened at the end of the day:
- 900E (from 2750N to 3300N) dirt shoulder and seal coat
- 700E (from 2700N to 3070N) add rock
- 2500N (from 400E to CH5) culvert work C-210
- 1200E (from 3300N to 3400N) field tile repair
- 1400E (from 3100N to 3200N) soil cement stabilization
- 3200N (from 900E to CH2) dirt shoulders
The following roads will be closed and reopened on 05/07/24:
- 1500E (from 3200N to 3300N) soil cement cure
The following roads will be closed and reopened on 05/08/24:
- 3300N (from 1400E to 1500E) soil cement cure
The following roads will be closed and reopened on 05/09/24:
- 1400E (from 3200N to 3300N) soil cement cure
The following roads will be closed and reopened on 05/10/24
- 1100E (from 3300N to 3400N) soil cement cure
In addition, the following work is anticipated for Tuesday 05/07/2024:
Tuesday 05/07/2024: Box Culvert Installation 2500 N between 400 E and CH 5 (C-210 RipRap)
Cement Stabilization 3100 N between CH 2 and 1400 E
Pre. Pulverization 1200 E between 3300 N and 3400 N
Add Rock 700 E between 2750 N and 3070 N
4" Aggregate Cap 1500 E between 3200 N and 3300 N
Anticipated work can be altered by weather, equipment breakdowns, or any other unforeseen circumstance.