Plan of the Day: May 06

Tne following roads will be closed and reopened at the end of the day:

  • 900E (from 2750N to 3300N) dirt shoulder and seal coat 
  • 700E (from 2700N to 3070N) add rock
  • 2500N (from 400E to CH5) culvert work C-210
  • 1200E (from 3300N to 3400N) field tile repair
  • 1400E (from 3100N to 3200N) soil cement stabilization
  • 3200N (from 900E to CH2) dirt shoulders

The following roads will be closed and reopened on 05/07/24:

  • 1500E (from 3200N to 3300N) soil cement cure

The following roads will be closed and reopened on 05/08/24:

  • 3300N (from 1400E to 1500E) soil cement cure

The following roads will be closed and reopened on 05/09/24:

  • 1400E (from 3200N to 3300N) soil cement cure

The following roads will be closed and reopened on 05/10/24

  • 1100E (from 3300N to 3400N) soil cement cure

 

In addition, the following work is anticipated for Tuesday 05/07/2024:

Tuesday 05/07/2024:  Box Culvert Installation 2500 N between 400 E and CH 5 (C-210 RipRap)
                                    Cement Stabilization     3100 N between CH 2 and 1400 E
                                    Pre. Pulverization          1200 E between 3300 N and 3400 N
                                    Add Rock                        700 E between 2750 N and 3070 N
                                    4" Aggregate Cap          1500 E between 3200 N and 3300 N

Anticipated work can be altered by weather, equipment breakdowns, or any other unforeseen circumstance.