The following road segments will be closed May 07 and reopened end of day May 07:
- 2500 N (from 400 E to CH 5) Culvert C-210
- 1200 E (from 3200 N to 3300 N) Culverts C-23 and C-24 Rip Rap
- 3200 N (from CH 2 to 1200 E) Pre Pulverize
- 700 E (from 2750 N to 3070 N) Add Rock
- 900 E (from 2750 N to 3300 N) Shoulder work and Oil/Chip
- 3200 N (from 900 E to CH 2) Shoulder work
The following road segments will be closed May 07 with intended reopening end of day May 08
- 1500 E (from 3200 N to 3300 N) Soil Cement Cure
The following road segments will be closed May 07 with intended reopening end of day May 09
- 3300 N (from 1400 E to 1500 E) Soil Cement Cure
The following road segments will be closed May 07 with intended reopening end of day May 14
- 3100 N (from CH 2 to 1400 E) Soil Cement Stabilization
Plan is subject to change due to weather and other unforeseen circumstances
Do you like this post?