The following road segments will be closed May 07 and reopened end of day May 07:

  • 2500 N (from 400 E to CH 5) Culvert C-210
  • 1200 E (from 3200 N to 3300 N) Culverts C-23 and C-24 Rip Rap 
  • 3200 N (from CH 2 to 1200 E) Pre Pulverize
  • 700 E (from 2750 N to 3070 N) Add Rock
  • 900 E (from 2750 N to 3300 N) Shoulder work and Oil/Chip
  • 3200 N (from 900 E to CH 2) Shoulder work

The following road segments will be closed May 07 with intended reopening end of day May 08

  • 1500 E (from 3200 N to 3300 N) Soil Cement Cure

The following road segments will be closed May 07 with intended reopening end of day May 09

  • 3300 N (from 1400 E to 1500 E) Soil Cement Cure

The following road segments will be closed May 07 with intended reopening end of day May 14

  • 3100 N (from CH 2 to 1400 E) Soil Cement Stabilization

 