The following roads will be closed May 08 and reopened by end of day:
- 2500 N (from 400 E to CH 5) Culvert C-210
- 3100 N (from CH 2 to 1400 E) Soil Cement Stabilization
- 3200 N (from CH2 to 1200 E) Pre-pulverization
- 700 E (from 2750 N to 3070 N) Roadway Prep
- 900 E (from 2750 N to 3300 N) Shoulder Work
- 3200 N (from 900 E to CH 2) Shoulder Work
- 1500 E (from 3200 N to 3300 N) Soil Cement Cure
The following roads will be closed May 08 and planned to reopen May 09
- 3300 N (from 1400 E to 1500 E) Soil Cement Cure
The following roads will be closed May 08 and planned to reopen May 10
- 1400 E (from 3100 N to 3300 N) Soil Cement Cure
In addition, the following work is anticipated for Thursday 05/09/2024 and Friday 05/10/2024:
Thursday 05/09/2024: Culvert Installation (C-144) 700 E between 2750 N and 2900 N
Cement Stabilization 3200 N between CH 2 and 1200 E
Pre Pulverization 1200 E between 3300 N and 3400 N
Add Rock 700 E between 2750 N and 3070 N
Add Rock 3070 N between 700 E and 800 E
Dirt Shoulders 3200 N between 900 E and CH 2
Dirt Shoulders 900 E between 2750 N and US 150
Friday 05/10/2024: Culvert Installation (C-144) 700 E between 2750 N and 2900 N
Cement Stabilization 1200 E between 3300 N and 3400 N
Pre Pulverization 1200 E between 3200 N and 3300 N
Add Rock 700 E between 2900 N and 3070 N
Add Rock 3070 N between 700 E and 800 E
Dirt Shoulders 3200 N between 900 E and CH 2
Dirt Shoulders 900 E between 2750 N and US 150
Anticipated work can be altered by weather, equipment breakdowns, or any other unforeseen circumstance.