Plan of the Day: May 13

The following roads will be closed and reopened at the end of the day:

  • 800E (from 2600N to 2700N) culvert work C-50
  • 1200E (from 3200N to 3400N) soil cement stabilization
  • 3200N (from 1100E to 1200E) pre-pulverization
  • 700E (from 2750N to 3070N) dirt shoulders
  • 3070N (from 700E to 800E) dirt shoulders
  • 1100E (from 3300N to 3400N) 
  • 3100N (from CH2 to 1400E) soil cement cure

The following roads will be closed and reopened on 05/14/24:

  • 3200N (from 1200E to CH2) soil cement cure

The following roads will be closed and reopened on 05/15/24:

  • 1200E (from 3300N to 3400N) soil cement cure

In addition, the following work is anticipated for Tuesday 05/14/2024:

Tuesday 05/14/2024:  Culvert Installation (C-50) Riprap   800 E between 2600 N and 2700 N
                                    Cement Stabilization                      3200 N between 1100 E and 1200 E
                                    Pre Pulverization                            3200 N between 1000 E and 1100 E
                                    4" Aggregate Cap                           1500 E between 3200 N and 3300 N

Anticipated work may be altered by weather, equipment breakdown, or any other unforeseen circumstances.