The following roads will be closed and reopened at the end of the day:
- 800E (from 2600N to 2700N) culvert work C-50
- 1200E (from 3200N to 3400N) soil cement stabilization
- 3200N (from 1100E to 1200E) pre-pulverization
- 700E (from 2750N to 3070N) dirt shoulders
- 3070N (from 700E to 800E) dirt shoulders
- 1100E (from 3300N to 3400N)
- 3100N (from CH2 to 1400E) soil cement cure
The following roads will be closed and reopened on 05/14/24:
- 3200N (from 1200E to CH2) soil cement cure
The following roads will be closed and reopened on 05/15/24:
- 1200E (from 3300N to 3400N) soil cement cure
In addition, the following work is anticipated for Tuesday 05/14/2024:
Tuesday 05/14/2024: Culvert Installation (C-50) Riprap 800 E between 2600 N and 2700 N
Cement Stabilization 3200 N between 1100 E and 1200 E
Pre Pulverization 3200 N between 1000 E and 1100 E
4" Aggregate Cap 1500 E between 3200 N and 3300 N
Anticipated work may be altered by weather, equipment breakdown, or any other unforeseen circumstances.