Following roads will be closed for roadwork and reopened at the end of the day:
- 900E (from 3200N to 3300N) C-34 culvert work
- 1200E (from 3200N to 3300N) soil cement stabilization
- 3200N (from 1100E to 1200E) soil cement stabilization
- 1500E (from 3200N to 3300N) aggregate capping
- 3300N (from 1400E to 1500E) aggregate capping
- 3200N (from 900E to 1200E) dirt shoulders
Following roads will be closed for roadwork and reopened on 05/20/24:
- 1200E (from 3200N to 3400N) soil cement cure
In addition, the following work is anticipated for Thursday 05/16/2024 and Friday 05/17/2024:
Thursday 05/16/2024: Culvert Installation 3070 N between 700 E and 800 E (C-281)
700 E between 2900 N and 3070 N (C-282)
Cement Stabilization 3200 N between 1000 E and 1100 E
Pre pulverization 3200 N between 900 E and 1000 E
4" Aggregate Cap 1400 E between 3100 N and 3300 N
Dirt Shoulders 3200 N between 900 E and 1200 E
HMA Patching CH 10 between 900 E and 1200 E
Friday 05/17/2024: Culvert Installation 800 E between 2600 N and 2700 N (C-50)
Cement Stabilization 1100 E between 3200 N and 3300 N
3200 N between 10000 E and 1100 E
4" Aggregate Cap 3100 N between CH 2 and 1400 E
HMA Patching CH 10 between 900 E and 1200 E
Anticipated work may be altered by weather conditions, equipment breakdowns, or any other unforeseen circumstance.