Plan of the Day: May 16

Following roads will be closed and reopened at the end of the day:

  • 3070N (from 700E to 800E) C-281 culvert work
  • 700E (from 2900N to 3070N) C-282 culvert work
  • 3200N (from 900E to 1100E) pre-pulverization
  • CH5 (from IL RT10 to County Line) CIR - road will be open to traffic with flaggers in work zone
  • 1400E (from 3100N to 3300N)
  • CH10 (from 900E to 1200E) patching (road will be open to traffic and flaggers in work zone)

Following roads will be closed and reopened on 05/21/24

  • 1200E (from 3200N to 3400N) soil cement cure

Following roads will be closed and reopened on 05/22/24

  • 3200E (from 1100E to 1200E) soil cement cure

Following roads will be closed and reopened on 05/23/24

  • 3200N (from 1100E to 1200E) soil cement stabilization

Following roads will be closed and reopened on 05/23/24

  • 1100E (from 3200E to 3300E) soil cement stabilization

In addition, the following work is anticipated for Friday 05/17/2024:

Friday 05/17/2024:      Culvert Installation       800 E between 2600 N and 2700 N  (C-50)
                                    Cement Stabilization   1100 E between 3200 N and 3300 N
                                                                        3200 N between 10000 E and 1100 E
                                     4" Aggregate Cap       3100 N between CH 2 and 1400 E
                                     HMA Patching             CH 10 between 900 E and 1200 E

Anticipated work may be altered by weather conditions, equipment breakdowns, or any other unforeseen circumstance.