Following roads will be closed and reopened at the end of the day:
- 3070N (from 700E to 800E) C-281 culvert work
- 700E (from 2900N to 3070N) C-282 culvert work
- 3200N (from 900E to 1100E) pre-pulverization
- CH5 (from IL RT10 to County Line) CIR - road will be open to traffic with flaggers in work zone
- 1400E (from 3100N to 3300N)
- CH10 (from 900E to 1200E) patching (road will be open to traffic and flaggers in work zone)
Following roads will be closed and reopened on 05/21/24
- 1200E (from 3200N to 3400N) soil cement cure
Following roads will be closed and reopened on 05/22/24
- 3200E (from 1100E to 1200E) soil cement cure
Following roads will be closed and reopened on 05/23/24
- 3200N (from 1100E to 1200E) soil cement stabilization
Following roads will be closed and reopened on 05/23/24
- 1100E (from 3200E to 3300E) soil cement stabilization
In addition, the following work is anticipated for Friday 05/17/2024:
Friday 05/17/2024: Culvert Installation 800 E between 2600 N and 2700 N (C-50)
Cement Stabilization 1100 E between 3200 N and 3300 N
3200 N between 10000 E and 1100 E
4" Aggregate Cap 3100 N between CH 2 and 1400 E
HMA Patching CH 10 between 900 E and 1200 E
Anticipated work may be altered by weather conditions, equipment breakdowns, or any other unforeseen circumstance.