Plan of the Day: May 17

Following roads will be closed and reopened at the end of the day:

  • 700E (from 2150N to IL RT 10) C-279 culvert work
  • 3200N (from 900E to 1000E) pre-pulverization
  • CH5 (from IL RT10 to County Line) CIR (work zone will be flagged)
  • 1400E (from 3100N to 3300N)
  • 3100N (from CH2 to 1400E)
  • CH10 (from 900E to 1200E) patching (work zone will be flagged)
  • 700E (from 2900N to 3070N) C-282 culvert work

Following roads will be closed and reopened on 05/20/24:

  • 1200E (from 3100N to 3200N) soil cement cure
  • 3200N (from 1100E to 1200E) soil cement cure

Following roads will be closed and reopened on 05/24/24

  • 3200N (from 1000E to 1100E) soil cement stabilization