Plan Of The Day: May 18

The following will be closed and reopened May 18:

  • 3100 N (from CH 2 to 1400 E)  Aggregate Capping

The following will be closed and reopened May 20:

  • 1200 E (from 3200 N to 3400 N) Soil Cement Cure

The following will be closed and reopened May 23:

  • 3200 N (from 1000 E to 1200 E) Soil Cement Cure

In addition, the following work is anticipated for Monday 05/20/2024 and Tuesday 05/21/2024:

Monday 05/20/2024:   Culvert Installation        2750 N between 600 E and 700 E (C-54)
                                    Cement Stabilization    3200 N between 900 E and 1000 E
                                                                            900 E between US 150 and I-74
                                    Pre Pulverization           3070 N between 700 E and 800 E
                                    C.I.R.                             CH 5 between IL Rt 10 and County Line
                                    4" Aggregate Cap          1200 E between 3300 N and 3400 N
                                    Dirt Shoulders                1400 E between 3100 N and 3300 N


Tuesday 05/21/2024:   Culvert Installation       700 E between IL Rt 10 and 2150 N (C-279)
                                     Cement Stabilization    3070 N between 700 E and 800 E
                                     Pre Pulverization           700 E between 2900 N and 3070 N
                                     C.I R.                             CH 5 between IL Rt 10 and County Line
                                     HMA                              CH 10 between 900 E and 1200 E
                                     Dirt Shoulders               1400 E between 3100 N and 3300 N