The following will be closed and reopened May 18:
- 3100 N (from CH 2 to 1400 E) Aggregate Capping
The following will be closed and reopened May 20:
- 1200 E (from 3200 N to 3400 N) Soil Cement Cure
The following will be closed and reopened May 23:
- 3200 N (from 1000 E to 1200 E) Soil Cement Cure
In addition, the following work is anticipated for Monday 05/20/2024 and Tuesday 05/21/2024:
Monday 05/20/2024: Culvert Installation 2750 N between 600 E and 700 E (C-54)
Cement Stabilization 3200 N between 900 E and 1000 E
900 E between US 150 and I-74
Pre Pulverization 3070 N between 700 E and 800 E
C.I.R. CH 5 between IL Rt 10 and County Line
4" Aggregate Cap 1200 E between 3300 N and 3400 N
Dirt Shoulders 1400 E between 3100 N and 3300 N
Tuesday 05/21/2024: Culvert Installation 700 E between IL Rt 10 and 2150 N (C-279)
Cement Stabilization 3070 N between 700 E and 800 E
Pre Pulverization 700 E between 2900 N and 3070 N
C.I R. CH 5 between IL Rt 10 and County Line
HMA CH 10 between 900 E and 1200 E
Dirt Shoulders 1400 E between 3100 N and 3300 N