Plan of the Day: May 20

Following roads will be closed and reopened at the end of the day:

  • 2750N (from 600E to 700E) C-54
  • 3070N (from 700E to 800E) pre-pulverization
  • CH5 (from IL route 10 to County Line) CIR (work zone will have flaggers)
  • 1200E (from 3300N to 3400N)
  • 1400E (from 3100N to 3300N) dirt shoulders

Following roads will be closed and reopened on 05/21/24:

  • 1200E (from 3200N to 3300N) soil cement cure

Following roads will be closed and reopened on 05/22/24:

  • 3200N (from 1000E to 1200E) soil cement cure

Following roads will be closed and reopened on 05/27/24:

  • 3200N (from 900E to 1000E)  soil cement stabilization
  • 900E (from US150 to I74) soil cement stabilization

In addition, the following work is anticipated for Tuesday 05/21/2024:

Tuesday 05/21/2024:   Culvert Installation       700 E between IL Rt 10 and 2150 N (C-279)
                                     Cement Stabilization    3070 N between 700 E and 800 E
                                     Pre Pulverization           700 E between 2900 N and 3070 N
                                     C.I R.                             CH 5 between IL Rt 10 and County Line
                                     HMA                              CH 10 between 900 E and 1200 E
                                     Dirt Shoulders               1400 E between 3100 N and 3300 N



Anticipated work may be altered by weather, equipment breakdowns, or any other unforeseen circumstance