Following roads will be closed and reopened at the end of the day:
- 2750N (from 600E to 700E) C-54
- 3070N (from 700E to 800E) pre-pulverization
- CH5 (from IL route 10 to County Line) CIR (work zone will have flaggers)
- 1200E (from 3300N to 3400N)
- 1400E (from 3100N to 3300N) dirt shoulders
Following roads will be closed and reopened on 05/21/24:
- 1200E (from 3200N to 3300N) soil cement cure
Following roads will be closed and reopened on 05/22/24:
- 3200N (from 1000E to 1200E) soil cement cure
Following roads will be closed and reopened on 05/27/24:
- 3200N (from 900E to 1000E) soil cement stabilization
- 900E (from US150 to I74) soil cement stabilization
In addition, the following work is anticipated for Tuesday 05/21/2024:
Tuesday 05/21/2024: Culvert Installation 700 E between IL Rt 10 and 2150 N (C-279)
Cement Stabilization 3070 N between 700 E and 800 E
Pre Pulverization 700 E between 2900 N and 3070 N
C.I R. CH 5 between IL Rt 10 and County Line
HMA CH 10 between 900 E and 1200 E
Dirt Shoulders 1400 E between 3100 N and 3300 N
Anticipated work may be altered by weather, equipment breakdowns, or any other unforeseen circumstance