Following roads will be closed and reopened at the end of the day:
- 700E (from 2900N to 3070N) pre-pulverization
- CH5 (from IL RT10 to County Line) CIR (work zone will have flaggers)
- CH10 (from 900E to 1100E) HMA binder
- 1100E (from 3300N to 3400N) seal coat
- 1200E (from 3300N to 3400N) seal coat
- 1500E (from 3200N to 3300N) seal coat
- 1400E (from 3100N to 3300N) seal coat
- 3100N (from CH2 to 1400N) seal coat
Following roads will be closed and reopened on 05/27/24:
- 900E (from US150 to I74) soil cement cure
- 3200N (from 900E to 1000E) soil cement cure
Following roads will be closed and reopened on 05/29/24:
- 3070N (from 700E to 800E) soil cement stabilization
In addition, the following work is anticipated for Thursday 05/23/24 and Friday 05/24/2024:
Thursday 05/23/2024: Culvert Installation 775 E between 2050 N and 2150 N (C-41 Toewalls)
Cement Stabilization 700 E between 2900 N and 3070 N
HMA Binder CH 10 between 900 E and 1000 E
Dirt Shoulders 1400 E between 3100 N and 3300 N
3100 N between CH 2 and 1400 E
Friday 05/24/2024: Culvert Installation 2400 N between 400 E and CH 5 (C-100 Toewalls)
Cement Stabilization 700 E between 2750 N and 2900 N
Pre Pulverization 700 E between 2700 N and 2750 N
Shoulders CH 10 between 900 E and 1200 E
Dirt Shoulders 3100 N between CH 2 and 1400 E
1500 E between 3200 N and 3300 N
Anticipated work may be altered by weather, equipment breakdowns, or any other unforeseen circumstance.