Following roads will be closed and reopened at the end of the day:
- 775E (from 2050N to 2150N) C-41 (toewalls)
- 700E (from 2750N to 2900N) pre-pulverization
- CH10 (from 900E to 1200E) HMA/Shoulders (work zone flagged)
- 1500N (from 3200N to 3300N) dirt shoulders
- 3100N (from CH2 to 1400E) dirt shoulders
- 3300 N (from 1400 E to 1500 E) dirt shoulders
Following roads will be closed and reopened on 05/27/24:
- 3200N (from 900E to 1000E) soil cement cure
Following roads will be closed and reopened on 05/29/24:
- 3070N (from 700E to 800E) soil cement cure
Following roads will be closed and reopened on 05/30/24:
- 700E (from 2900N to 3070N) soil cement stabilization
In addition, the following work is anticipated for Friday 05/24/2024:
Friday 05/24/2024: Culvert Installation 2400 N between 400 E and CH 5 (C-100 Toewalls)
Cement Stabilization 700 E between 2750 N and 2900 N
Pre Pulverization 700 E between 2700 N and 2750 N
Shoulders CH 10 between 900 E and 1200 E
Dirt Shoulders 3100 N between CH 2 and 1400 E
1500 E between 3200 N and 3300 N
Anticipated work may be altered by weather, equipment breakdowns, or any other unforeseen circumstance.