Plan of the Day: May 23

Following roads will be closed and reopened at the end of the day:

  • 775E (from 2050N to 2150N) C-41 (toewalls)
  • 700E (from 2750N to 2900N) pre-pulverization
  • CH10 (from 900E to 1200E) HMA/Shoulders (work zone flagged)
  • 1500N (from 3200N to 3300N) dirt shoulders
  • 3100N (from CH2 to 1400E) dirt shoulders
  • 3300 N (from 1400 E to 1500 E) dirt shoulders

Following roads will be closed and reopened on 05/27/24:

  • 3200N (from 900E to 1000E) soil cement cure

Following roads will be closed and reopened on 05/29/24:

  • 3070N (from 700E to 800E) soil cement cure

Following roads will be closed and reopened on 05/30/24:

  • 700E (from 2900N to 3070N) soil cement stabilization

 

In addition, the following work is anticipated for Friday 05/24/2024:

  Friday 05/24/2024:    Culvert Installation            2400 N between 400 E and CH 5 (C-100 Toewalls)
                                    Cement Stabilization          700 E between 2750 N and 2900 N
                                    Pre Pulverization                700 E between 2700 N and 2750 N
                                    Shoulders                           CH 10 between 900 E and 1200 E
                                    Dirt Shoulders                    3100 N between CH 2 and 1400 E
                                                                               1500 E between 3200 N and 3300 N

 Anticipated work may be altered by weather, equipment breakdowns, or any other unforeseen circumstance.