Plan of the Day: May 24

Following roads will be closed and reopened at the end of the day:

  • 2400N (from 400E to CH5) C-1 (Toewalls)
  • CH10 (from 900E to 1200E) shoulders (work zone with flaggers)
  • 3100N (from CH2 to 1400E) dirt shoulders
  • 1500E (from 3200N to 3300N) dirt shoulders
  • 3300N (from 1400E to 1500E) dirt shoulders
  • 3200N (from CH2 to 1200E) aggregate capping

Following roads will be closed and reopened on 05/28/24:

  • 3070N (from 800E to 900E) soil cement cure

Following roads will be closed and reopened on 05/30/24:

  • 700E (from 3070N to 2900N) soil cement cure

Following roads will be closed and reopened on 05/31/24:

  • 700E (from 2750N to 2900N) soil cement stabilization
  • 700E (from 2750N to 2900N) pre-pulverization