Following roads are closed and will be reopened on 05/29/24:
- 3070N (from 700E to 800E) soil cement cure
Following roads are closed and will be reopened on 05/30/24:
- 700E (from 2750N to 3070N) soil cement cure
There will be no work on public roads tomorrow or Monday 05/27/24 (Memorial Day). The POD and POD Map shows road segments closed for soil cement cure. Anticipated work for Tuesday 05/28/2024 will be:
Culvert Installation : 2400 N between 400 E and CH-5 (C-100)
Cement Stabilization: 700 E between 2750 E and 2900 E
4" Aggregate Cap: 3200 N between CH 2 and 1100 E
Add Rock: 2750 N between CH 5 and 700 E
Anticipated work may be altered by weather, equipment breakdown, or any other unforeseen circumstance.