Following roads are closed and will be reopened at the end of the day:
- 2400N (from 400E to CH5) C-100
- 900E (from 2600N to 2750N) pre-pulverization
- 3200N (from 1100E to CH2) aggregate capping
- 2750N (from CH5 to 700E) add rock
Following roads are closed and will be reopened on 05/29/24:
- 3070N (from 700E to 800E) soil cement cure
Following roads are closed and will be reopened on 06/01/24:
- 700E (from 2900N to 3070N) soil cement cure
Following roads are closed and will be reopened on 06/04/24:
- 700E (from 2750N to 2900N) soil cement stabilization