Plan of the Day: May 29

Following roads will be closed and reopened at the end of the day:

  • 2400N (from 400E to CH5) C-100
  • 3200N (from 900E to 1200E)
  • 2750N (from 2750N to 1000E) add rock
  • 2700N (from 700E to 800E) add rock

Following roads will be closed and reopened on 06/04/24:

  • 700E (from 2750N to 2900N) soil cement stabilization 
  • 700E (from 2750N to 3070N) soil cement cure
  • 900E (from 2600N to 2750N) soil cement stabilization

In addition, the following work is anticipated for Thursday 05/30/24 and Friday 05/31/24:

Thursday 05/30/24:   Culvert Installation      775E between 2050N and 2150N (C-100)
                                  Cement Stabilization   900E between 2600N and 2750N
                                  Pre Pulverization        2750N between CH 5 and 600E
                                  4" Aggregate Cap       3200N between 900E and 1100E
                                  Add Rock                    2750N between 700E and 1000E

Friday 05//31/24:       Culvert Installation       775E between 2050N and 2150N (C-41)
                                  Cement Stabilization   2750N between CH 5 and 600E
                                  Pre Pulverization         2750N between 600E and 700E
                                  4" Aggregate Cap        3200N between 900E and 1000E
                                                                         900E between US 150 and I-74
                                   Add Rock                    2750N between 900E and 1000E

Anticipated work may be altered by weather conditions, equipment breakdowns, or any other unforeseen circumstances.