Following roads will be closed and reopened at the end of the day:
- 2400N (from 400E to CH5) C-100
- 3200N (from 900E to 1200E)
- 2750N (from 2750N to 1000E) add rock
- 2700N (from 700E to 800E) add rock
Following roads will be closed and reopened on 06/04/24:
- 700E (from 2750N to 2900N) soil cement stabilization
- 700E (from 2750N to 3070N) soil cement cure
- 900E (from 2600N to 2750N) soil cement stabilization
In addition, the following work is anticipated for Thursday 05/30/24 and Friday 05/31/24:
Thursday 05/30/24: Culvert Installation 775E between 2050N and 2150N (C-100)
Cement Stabilization 900E between 2600N and 2750N
Pre Pulverization 2750N between CH 5 and 600E
4" Aggregate Cap 3200N between 900E and 1100E
Add Rock 2750N between 700E and 1000E
Friday 05//31/24: Culvert Installation 775E between 2050N and 2150N (C-41)
Cement Stabilization 2750N between CH 5 and 600E
Pre Pulverization 2750N between 600E and 700E
4" Aggregate Cap 3200N between 900E and 1000E
900E between US 150 and I-74
Add Rock 2750N between 900E and 1000E
Anticipated work may be altered by weather conditions, equipment breakdowns, or any other unforeseen circumstances.