The following roads will be closed and reopened at the end of the day:
- 775E (from 2050N to 2150N) C-41 (overnight closure)
- 2750N (from 600E to 900E) pre-pulverization
- 3200N (from 900E to 1100E)
- 1100E (from 3200N to 3300N)
- 900E (from US-150 to I74) aggregate capping
- 3300N (from 1400E to 1500E) aggregate capping
- 2750N (from 700E to 1000E) add rock
The following roads will be closed and reopened on 06/04/24:
- 900E (from 2600N to 2750N) soil cement stabilization
- 2750N (from CH5 to 600E) soil cement stabilization
- 700E (from 2750N to 2900N) soil cement cure
In addition, the following work is anticipated for Friday 05/31/24:
Friday 05//31/24: Culvert Installation 775E between 2050N and 2150N (C-41)
Cement Stabilization 2750N between CH 5 and 600E
Pre Pulverization 2750N between 600E and 700E
4" Aggregate Cap 3200N between 900E and 1000E
900E between US 150 and I-74
Add Rock 2750N between 900E and 1000E
Anticipated work may be altered by weather conditions, equipment breakdowns, or any other unforeseen circumstances.