Plan of the Day: May 30

The following roads will be closed and reopened at the end of the day:

  • 775E (from 2050N to 2150N) C-41 (overnight closure)
  • 2750N (from 600E to 900E) pre-pulverization
  • 3200N (from 900E to 1100E)
  • 1100E (from 3200N to 3300N)
  • 900E (from US-150 to I74) aggregate capping
  • 3300N (from 1400E to 1500E) aggregate capping
  • 2750N (from 700E to 1000E) add rock 

The following roads will be closed and reopened on 06/04/24:

  • 900E (from 2600N to 2750N) soil cement stabilization
  • 2750N (from CH5 to 600E) soil cement stabilization
  • 700E (from 2750N to 2900N) soil cement cure

In addition, the following work is anticipated for Friday 05/31/24:

Friday 05//31/24:       Culvert Installation       775E between 2050N and 2150N (C-41)
                                  Cement Stabilization   2750N between CH 5 and 600E
                                  Pre Pulverization         2750N between 600E and 700E
                                  4" Aggregate Cap        3200N between 900E and 1000E
                                                                         900E between US 150 and I-74
                                   Add Rock                    2750N between 900E and 1000E

Anticipated work may be altered by weather conditions, equipment breakdowns, or any other unforeseen circumstances.