Plan of the Day: November 14

Roadwork for 11/14/24:

  • 2750N (from 800E to 900E) C-52 extension - partial closure, roads will be reopened at the end of the day
  • 3200N (from 1400E to 1500E) roadway preparation - full closure, roads will be reopened at the end of the day
  • 700E (from IL RT10 to 2400N) crane crossing - full closure from 3pm to 6pm

    

In addition, the following work is anticipated for Friday 11/15/24:

Friday 11/15/24:        RCCP Installation                                  3200N between 1400E and 1500E
                                  Roadway Prep.                                      3200N between 1400E and 1500E

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.