Plan of the Day: November 2

Roadwork for 11/02/24:

  • Permanent seeding in Blue Ridge Twp. (no lane closures)

In addition, the following work is anticipated for Monday 11/04/24 and Tuesday 11/05/24:

Monday 11/04/24:    Culvert Extensions at C-138   900E at CH 10
                                 Milling entrance returns          900E at US 150
                                 Permanent Seeding in Blue Ridge Twp.

Tuesday 11/05/24:   Culvert Extension at C-52       2750N between 800E and 900E
                                 HMA entrance returns            900E at US 150
                                 Permanent seeding in Blue Ridge Twp.


Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.