Plan of the Day: November 23

There will be no roadwork for 11/22/24.

Full closure at 800E (from IL RT10 to 2400N) for crane crossing from 12pm to 3pm.

 



In addition, the following work is anticipated for Tuesday 11/26/24:

Tuesday 11/26/24:   Culvert Installation CH 10 between 1030E and 1100E (C-33)

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.