Roadwork for 11/25/24:
- 2150N (from 600E to 675E) full lane closure and will be reopened at the end of the day culvert extension at C-220.
- 800E (from 2500E to 2600E) full lane closure for crane crossing from 9am to 12pm
In addition, the following work is anticipated for Tuesday 11/26/24:
Tuesday 11/26/24: Culvert Installation CH 10 between 1030E and 1100E (C-33)
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.