Plan Of The Day: November 6

The following will be partially closed and reopened 11/06 end of day

  • 900E (from 3200N to CH 10) Culvert extension C-138 
  • 900E (from US 150 to I-74 overpass) Milling aprons in preparation for Hot Mix Asphalt

In addition, the following work is anticipated for Thursday 11/07/24 and Friday 11/08/24:

Thursday 11/07/24:  Culvert Extension at C-52  2750N between 800E and 900E
                                 HMA returns 900E and US 150
                                 Permanent Seeding in Blue Ridge Twp.

Friday 11/08/24:      Culvert Extension at C-52  2750N between 800E and 900E
                                Permanent Seeding in Blue Ridge Twp.

Anticipated work may be altered by inclement weather, wet ground conditions or any other unforeseen circumstances