Plan of the Day: October 09

Roadwork on 10/09/24:

  • CH5 (from 2400N to 2750N) will be partially closed and reopened at the end of the day for HMA tapers at sideroad returns and dirt shoulders at "S" curve. 
  • 2500N (from 700E to 800E) will be closed for crane crossing from 8am to 10am. 
  • Field Entrance culverts in Blue Ridge Twp. (no lane closures)
  • Permanent seeding in Blue Ridge Twp. (no lane closures)
  • Permanent culverts at private access roads (no lane closures)

In addition, the following work is anticipated for Thursday 10/10/24 and Friday 10/11/24:

Thursday 10/10/24:     Field Entrance Culverts in Blue Ridge Twp.

                                    HMA sideroad returns and dirt shoulders on CH 5 ("S" curve)
                                    Permanent Seeding in Blue Ridge Twp.

Friday 10/11/24:         Field entrance culverts in Blue Ridge Twp.
                                   Dirt Shoulders on CH 5 ("S" curve)
                                   Permanent Seeding in Blue Ridge Twp.

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.