Roadwork on 10/09/24:
- CH5 (from 2400N to 2750N) will be partially closed and reopened at the end of the day for HMA tapers at sideroad returns and dirt shoulders at "S" curve.
- 2500N (from 700E to 800E) will be closed for crane crossing from 8am to 10am.
- Field Entrance culverts in Blue Ridge Twp. (no lane closures)
- Permanent seeding in Blue Ridge Twp. (no lane closures)
- Permanent culverts at private access roads (no lane closures)
In addition, the following work is anticipated for Thursday 10/10/24 and Friday 10/11/24:
Thursday 10/10/24: Field Entrance Culverts in Blue Ridge Twp.
HMA sideroad returns and dirt shoulders on CH 5 ("S" curve)
Permanent Seeding in Blue Ridge Twp.
Friday 10/11/24: Field entrance culverts in Blue Ridge Twp.
Dirt Shoulders on CH 5 ("S" curve)
Permanent Seeding in Blue Ridge Twp.
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.