Plan of the Day: October 2

Roadwork for 10/02/24:

  • Field Entrance culverts in Blue Ridge Twp. (no lane closure)
  • CH10 (from 900E to 1200E) will be closed and reopened at the end of the day for HMA patching over culverts

In addition, the following work is anticipated for Thursday 10/03/24 and Friday 10/04/24:

Thursday 10/02/24:     Field Entrance culverts in Blue Ridge Twp.
                                    Off load culvert extensions
                                    Field Entrance aggregate in Blue Ridge Twp.

Friday 10/04/24:        Culvert Extensions 700E between 2750N and 3070N
                                  Field Entrance aggregate in Blue Ridge Twp.

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstance