Roadwork for 10/03/24:
- Field Entrance culverts in Blue Ridge Twp (no lane closures)
- Field Entrance aggregate in Blue Ridge Twp (no lane closures)
In addition, the following work is anticipated for Friday 10/04/24:
Friday 10/04/24: Culvert Extensions 700E between 2750N and 3070N
Field Entrance aggregate in Blue Ridge Twp.
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.