Plan of the Day: September 18

Road will be closed through 09/19/24:

  • 2500N (from 700E to 800E)

 

Additional roadwork (no lane closures):

  • F.E. culverts in Goose Creek Twp.
  • Permanent Seeding in Blue Ridge Twp.
  • F.E. agggregate in Blue Ridge Twp.

In addition, the following work is anticipated for Thursday 09/19/24 and Friday 09/20/2024:

Thursday 09/19/24:     Field Entrance Culverts in Goose Creek Twp.
                                    Field Entrance Aggregate in Blue Ridge Twp.
                                    Permanent Seeding in Blue Ridge Twp.

Friday 09/20/24:          Field Entrance Culverts in Goose Creek Twp.
                                    Field entrance Aggregate in Blue Ridge Twp.
                                    Permanent Seeding in Blue Ridge Twp

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.