700E (from 2400N to 2500N) road will be closed and reopened on 09/21/24 for C-103 extension work.
2500N (from 700E to 800E) road will be closded and reopened on 09/22/24 for road repair.
In addition, the following work is anticipated for Monday 09/23/24/ and Tuesday 09/24/2024:
Monday 09/23/24: Road Repair 2500N between 700E and 800E
Field Entrance Culverts in Blue Ridge and Goose Creek Twp.
Field Entrance Aggregate in Blue Ridge Twp.
Permanent Seeding in Blue Ridge Twp.
Tuesday 09/24/24: Road Repair 2500N between 700E and 800E
Shoulder Repair 900E ("S" curve) south of US 150
Field Entrance Culverts in Blue Ridge Twp.
Field Entrance Aggregate in Blue Ridge Twp.
Permanent Seeding in Blue ridge Twp.
Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.