Plan of the Day: September 30

Roadwork for 09/30/24:

  • 900E (from 2850N to US150) will be fully closed for aggregate shoulders at "S" curve. Construction traffic may use public to public cut thru.
  • 800E (from 2500N to 2600N) will be closed and reopened after crane crossing (8:00am to 10:00am)
  • 2500N (from 700E to 800E) will be closed and reopened after crane crossing (10:00am to Noon)
  • Field entrance culverts Goose Creek Twp. (no lane closure)
  • Permanent seeding in Blue Ridge Twp. (no lane closure)

In addition, the following work is anticipated for Tuesday 10/01/24:


Tuesday 10/01/24:    Aggregate Shoulders       700E between 2900N and 3070BN (at "S" curve)
                                 Field Entrance Culverts    Blue Ridge and Goose Creek Twp.
                                 Permanent Seeding          Blue Ridge Twp.

Anticipated work may be altered by inclement weather, equipment breakdown, or any other unforeseen circumstances.