Plan of the Day: September 9

Road work for 09/09/24:

  • CH10 (from 1100E to 1200E) C-30 Riprap (NO LANE CLOSURE)

Field Entrance Aggregate in Goose Creek and Blue Ridge Twp.

Permanent Seeding in Goose Creek Twp.

In addition, the following work is anticipated for Tuesday 09/10/24:

Tuesday 09/10/24:    RipRap @ C-30    CH 10 between 1100E and 1200E (No Lane Closure)
                                  Permanent Seeding in Goose Creek Township

                                  Field Entrance Aggregate in Goose Creek and Blue Ridge Townships

Anticipated work may be altered by inclement weather, equipment breakdowns, or any other unforeseen circumstances.