Plan of the Day: July 20 (Saturday)

The following roads will be closed and reopened at the end of the day: 800E (from 2150N to 2400N) dust control seal coat 2150N (from CH5 to 800E) dust control seal coat 775E (from 2050N to 2150N) seal coat 600E (from 2150N to 3rd street) seal coat The following roads will be closed and reopened on 07/25/24: 2600N (from County Line to CH5) soil cement cure The following roads will be closed and reopened on 07/27/24: 2400N (from CH5 to 700E) soil cement stabilization     Continue reading