PLAN OF THE DAY: May 07
The following road segments will be closed May 07 and reopened end of day May 07:
2500 N (from 400 E to CH 5) Culvert C-210
1200 E (from 3200 N to 3300 N) Culverts C-23 and C-24 Rip Rap
3200 N (from CH 2 to 1200 E) Pre Pulverize
700 E (from 2750 N to 3070 N) Add Rock
900 E (from 2750 N to 3300 N) Shoulder work and Oil/Chip
3200 N (from 900 E to CH 2) Shoulder work
The following road segments will be closed May 07 with intended reopening end of day May 08
1500 E (from 3200 N to 3300 N) Soil Cement Cure
The following road segments will be closed May 07 with intended reopening end of day May 09
3300 N (from 1400 E to 1500 E) Soil Cement Cure
The following road segments will be closed May 07 with intended reopening end of day May 14
3100 N (from CH 2 to 1400 E) Soil Cement Stabilization
Plan is subject to change due to weather and other unforeseen circumstances